  • FINAL FURNISHING DATE IS A QUESTION OF FACT

    … Construction liens need to be recorded within 90 days from the lienor’s final furnishing date on the project. This date is exclusive of punchlist or warranty work. The final furnishing date needs to be proven at trial to establish that the construction lien was timely recorded. If there is an evidentiary dispute as the final furnishing date…